Project Plan & Schedule

The Aleutian Islands Risk Assessment (AIRA) study is following the process setout in the National Academy of Sciences Report. The Study was conducted in two phases.

Phase A – Preliminary Risk Assessment included:

  • Establishment of the Advisory Panel,
  • Contracting a Risk Analysis Team,
  • Selecting a Peer Review Panel,
  • Drafting a spill risk report on vessel traffic and spill likelihood,
  • Developing a risk matrix and consequence analysis, and
  • Conducting a qualitative assessment and prioritization of risk reduction options.

Phase B – Focused Risk Assessment included:

  • Implementing the methodology, and
  • Developing and reporting findings and recommendations.

Phase A was completed in 2011 and Phase B was completed in 2015. All technical documents for both Phases are posted here.